dining_background

Construction Updates

Home > Construction Updates

Construction Updates

 

Last Updated: May 22, 2019

 

Johnson Center Meeting Room Painting

JC Meeting Room E, F, and G will undergo light touch up  painting of the white walls in the space, not the accent color walls on Thursday, May 23.

JC Meeting Room B, C, and D will undergo light touchup painting of the white walls in the space, not the accent color walls on Friday, May 24.

We have worked with The Office of University Events to alter folks around who may be impacted by this work. So may see an update in 25Live.

 

Johnson Center Exterior Door Project

The exterior doors of the Johnson Center project began on Monday, May 20. The current plan is to work one side of each entrance at a time leaving the other side open for egress/ingress. Each entrance will take approximately one week to complete. If you have any questions or issues related to this project please let Director Steve Morehouse know.

 

May 20 – May 25               Northeast Entrance (facing clock tower)

 

May 28 – June 1                 East Entrance (facing Hub)

 

June 3 – June 8                  South Entrance (ground floor)

 

June 10 – June 15             Northwest Entrance (facing Mason Pond Deck)

 

June 17 – June 22             West Entrance (facing CFA)

 

June 24 – June 29             Loading Dock area and other ground floor work

 

July 1 –  July 12                   Testing access control/punch list items/inspections

 

HUB Carpet Cleaning and Touch up Painting

Stanley Steemer will be onsite June 6 and 7 to clean the carpets and common area spaces of the top floor of the HUB

June 6 – HUB Meeting Room 3-4-5 and VIP I

June 7 – HUB Meeting Room 1-2, VIP II and III

The Common Areas will be cleaned between the two days

 

Johnson Center Carpet Cleaning and Touch up Painting

Stanley Steemer will be onsite June 10 and 11 to clean the carpets of the following meeting rooms:

June 10 – Meeting Room D, F, and G

June 11 – Meeting Room B,C, and E

Still waiting to determine which date works best for Meeting Room A.

 

During those dates listed above between 6 a.m. and 8 a.m. we will do light touch painting of the same spaces but not all. Some meeting rooms may have to wait until Winter break. Our priority will be to focus on rooms with the most visible wear and tear.

 

JC Loading Dock Compactor Door Replacement

Within the next week or two, we are hopeful the JC loading dock door, the one where the trash compactor is will be replaced due to recent damage. This should not impact deliveries or services but I wanted folks to be made aware just in case.